SCHEDULE |
||||||
Week |
Date |
Topic |
Reading |
Deliverable Due |
||
M |
VS |
WB |
||||
1 |
1/27 |
System Development in Perspective | 1 (17-26) |
I |
||
1/29 |
Business Information Systems | 2 (41-54) |
||||
2 |
2/3 |
System Development Life Cycle | 3, 2.1 |
|||
2/5 |
Design Team Formation | |||||
3 |
2/10 |
Prototyping | 21 |
PTC |
||
2/12 |
ACCESS | III |
||||
4 |
2/17 |
ACCESS | ||||
2/19 |
System Development Tools | 6 |
1 |
PTP |
||
5 |
2/24 |
System Development Tools | 6.1 |
|||
2/26 |
FIRST EXAMINATION | ACCESS |
||||
6 |
3/3 |
Initial Investigation | 4, 5 |
IPS |
||
3/5 |
Requirements Analysis | 7 |
2 |
CT 1 |
||
7 |
3/10 |
Alternative Generation | IIA |
CASE 1 |
||
3/12 |
Cost-Benefit Analysis | 8 (257-282) |
||||
8 |
3/17 |
Cost-Benefit Analysis | CT 2 |
|||
3/19 |
FHC Case Study | IIB |
||||
9 |
3/24 |
Preliminary Design/ System Study | 9 |
CASE 2 |
||
3/26 |
SECOND EXAMINATION | |||||
10 |
3/31 |
Design Principles | 10 |
8 |
CASE 3 |
|
4/2 |
Data Dictionary | 11 (347-355) |
CSD |
|||
11 |
4/7-11 | SPRING RECESS | ||||
12 |
4/14 |
Decision Tables | 11 (356-362) |
CASE 4 |
||
4/16 |
Screen Design | 14 (431-444) |
RPS |
|||
13 |
4/21 |
Output Design | 12 |
CT 3 |
||
4/23 |
Input Design | 13 |
CASE 5 |
|||
14 |
4/28 |
Input Design | URD |
|||
4/30 |
THIRD EXAMINATION | |||||
15 |
5/5 |
Data Storage Design | 15 |
CT 4 |
||
5/7 |
Change Management | IIC |
||||
16 |
5/12 |
Design Team Presentations | REGRADE PRT, IPP |
|||
5/14 |
Design Team Presentations | FSS, PE |
||||
17 |
* |
FOURTH EXAMINATION | ||||
* See schedule for final examination times. |