MIS 161 SCHEDULE
Date |
Topic |
Chapter |
Deliverables |
8/25 |
Introduction - Discuss the Syllabus |
|
|
8/27 |
|
||
9/1 |
Labor Day Holiday – No classes |
|
|
9/3 |
Lab: Scrum in 60 minutes |
|
|
9/8 |
|
|
|
9/10 |
Review projects - Form Groups |
|
Team Composition |
9/15 |
Review.pptx: Use Case Diagrams and User Stories |
Project Schedule |
|
9/17 |
Lab: Scrum planning |
|
|
9/22 |
Lab: User story development |
|
|
9/24 |
Lab: Sprint 1 |
|
Design Review |
9/29 |
Additional Readings: Oracle Design, Microsoft Design, Apple Design, Android Design |
Chapter 10 |
|
10/1 |
Lab: Sprint 2 |
Release 1 |
|
10/6 |
Chapter 11 |
||
10/8 |
Sprint 3 Lab |
|
|
10/13 |
Release 1 Class Demo |
|
|
10/15 |
Chapter 12 |
|
|
10/20 |
First Exam |
||
10/22 |
Chapter 13 |
Release 2 |
|
10/27 |
Chapter 14 |
||
10/29 |
Lab: System Implementation |
Release 3 |
|
11/3 |
|
System Implementation |
|
11/5 |
Lab: System Deployment |
|
|
11/10 |
Lab: Software Testing Setup |
|
|
11/12 |
|
System Deployment |
|
11/17 |
Lab: Software Testing Execution |
|
|
11/19 |
Lab: System Maintenance |
|
Project Testing |
11/24 |
Presentation Recording |
|
|
11/26 |
Presentation Recording |
|
Project Presentation |
12/1 |
Lab: Post Implementation Review |
|
|
12/3 |
Class Review |
|
PIER Report |
12/10 |
Final Exam @ 3:00 PM |
|
|